Identified Design Issue

The internal handrail will likely have a vertical section or an inconsistent height.

Departure from Deemed-to-Satisfy Provisions

Due to spatial constraints within the existing building, the first ascending riser from the mid-landing is not set forward at a depth of one stair tread, resulting in an angled section on the internal handrail as it turns around the intermediate landing.

The Performance Solution

While the existing stair mid-landing design will be accepted, the stairway must be upgraded to meet compliance with AS 1428.1 in all aspects, including two handrails, TGSIs, and contrasting nosing strips. Lighting will also be improved.

This example is a hypothetical scenario and must not be used for any specific project.

Assessments must be tailored for each project.

Contact us to learn more. We are experts at preparing Performance Solution Reports.

Disclaimer: This publication provides general information only and does not constitute legal, certification or project-specific advice. Requirements may vary between projects and change over time. Always verify the current NCC, legislation and applicable Australian Standards, and obtain project-specific advice where required.

Images: PICCI-supplied imagery is licensed to the publisher and may not be reproduced or modified without permission. Third-party content remains subject to its applicable licence. Images are illustrative unless stated otherwise.